Dunaújváros-Szekszárd stretch to be completed on time

Representatives from a consortium of companies building a 65-kilometre stretch of the M6 motorway between Dunaújváros and Szekszárd on Tuesday confirmed the project would be completed by the deadline on March 31, 2010.

Asphalt has been laid on 60% of the stretch and excavation work is 90% finished, said Porr technical director Bernhard Pawlitschko. The construction of the road has to be finished before the dead of winter, by the end of 2009, leaving only smaller tasks, such as painting the road, for the period until the end of March, he added. (MTI-ECONEWS)